Overview
JAK Hire was contacted on a Thursday morning by one of our regular customers requiring emergency temporary access at a UK power station. A critical issue on site meant crane and excavator access was required immediately, with matting needing to be installed the same day to prevent damage to underground services and sensitive ground conditions.
This case study demonstrates how JAK Hire responded rapidly to an urgent request, delivering a same-day temporary access solution that enabled essential works to proceed safely and without delay.
The Challenge
Emergency access projects place unique demands on planning, logistics and execution. In this instance, the client faced several immediate challenges:
- Urgent timeframe
The request was received on the morning of the works, leaving only hours to assess the site, mobilise equipment and install matting. - Sensitive underground services
The access route crossed areas containing critical underground infrastructure, requiring ground protection that could safely distribute load from heavy plant and lifting equipment. - Heavy machinery access
Cranes and excavators needed stable, reliable access without risk of ground failure or service disruption. - Ongoing operational site
The power station remained live throughout, meaning installation had to be efficient, controlled and compliant with site safety requirements.
Without a rapid and reliable emergency access solution, the planned works would have been delayed, potentially impacting wider project timelines.
The Solution
JAK Hire delivered a fast-response emergency temporary access solution using heavy-duty TuffTrak ground protection mats.
Rapid Assessment & Planning
- Immediate coordination with the client upon receiving the call.
- Fast site assessment to identify load requirements, access routes and underground service locations.
- Calculation of mat quantities to ensure full coverage while allowing safe crane and excavator movement.
Same-Day Installation
- TuffTrak mats were mobilised and delivered to site immediately.
- Installation was completed by 4pm the same day, creating a stable access route for heavy plant.
- Mats were positioned carefully to spread load evenly and protect underground services.
Ongoing Works
- The emergency installation enabled critical works to proceed without interruption.
- Additional areas requiring protection were identified during the works.
The Outcome
- Emergency temporary access installed within hours of the initial call.
- Safe crane and excavator access achieved without damage to underground services.
- No disruption to ongoing power station operations.
- Follow-on works secured, with JAK Hire returning for further planned access installations.
This rapid-response project highlights JAK Hire’s ability to support both emergency and planned works at high-risk, operational infrastructure sites.
Completed emergency temporary access installation delivered on a same day basis.
Temporary access platform installed to protect ground conditions and underground services.
Heavy duty TuffTrak matting installed to create a stable working area for cranes and excavators.
TuffTrak mats laid through a restricted access area to provide safe emergency vehicle access.
Emergency temporary access route installed using TuffTrak ground protection mats to allow safe vehicle and plant movement.
Customer Experience
“We needed emergency access installed immediately to keep the works moving. JAK Hire responded straight away and had everything in place the same day. The installation was efficient, and the protection over underground services gave us complete confidence.”
Need Emergency Temporary Access?
If you require emergency temporary access for utilities, infrastructure or construction projects, JAK Hire can respond quickly with reliable ground protection solutions. From same-day installations to planned follow-on works, our team ensures safe access for heavy plant while protecting the ground and services beneath.